After a break of almost 40 years, passenger trains began stopping at Lomma station and other stations along the Lomma Line again in December 2020. Work is now continuing on the second phase of the Lomma Line project, which includes new train stops in both Alnarp and Flädie. These stations are expected to be completed in December 2027.
On this page:
30 November: Car park at Biotronen/Navet to close
The car park at Biotronen/Navet will close ahead of construction of the new pedestrian and cycle underpass. The area will be closed to prepare for the relocation of utility services: shrubs, kerbs and asphalt will be removed. The car park will therefore close permanently.
Deliveries to Biotronen and other buildings, as well as emergency-service access, will be rerouted via an entrance north of Vegetum. This entrance will be widened to ensure access.
SLU’s information signs and the artwork Solsilen will be relocated as part of the work.

Please note: The timetable is subject to change as the project progresses.
Autumn 2026–spring 2027: Preparatory work
Preparatory work for the new station will take place during autumn 2026 and winter 2027. This includes sampling excavated material, marking out utility services and demarcating construction areas.
Extensive utility diversions will also begin during the winter and spring to enable construction of a new pedestrian and cycle underpass beneath the railway. Excavation for the underpass and construction of the station platforms will begin.
30 November 2026: Car park at Biotronen/Navet closes permanently
The car park will close ahead of construction of the new pedestrian and cycle underpass.
4 January 2027: Sundsvägen closes and traffic is diverted
The western section of Sundsvägen, towards Malmövägen, will close because of extensive utility diversions and heavy construction traffic in the area west of the level crossing.
The level crossing on Sundsvägen will be permanently closed to traffic. Information boards will be installed in advance, followed by signs and physical barriers when the closure takes effect.
Agricultural machinery will still be able to access entrances to the fields.
Cycle traffic will be diverted along certain sections throughout 2027 because of utility works and construction of the pedestrian and cycle underpass.
4 January–2 April 2027: Gravel car park by the plant collection gardens closed
The gravel car park west of the plant collection gardens will remain closed while utilities are diverted from Sundsvägen, across the car park and further west beneath the railway.
To protect tree roots, some excavation will be carried out by hand or using vacuum excavation equipment. This applies particularly to the lime trees along Sundsvägen, outside the student accommodation closest to the railway.
Deliveries to and from the Cultivation Unit will be possible by prior arrangement. Entrances to the plant collection gardens from the west will be temporarily closed.
4 January–18 July 2027: Utility diversions in stages
Extensive utility diversions will be carried out in stages in preparation for the new pedestrian and cycle underpass and train station.
The work will affect access in the area, including diversions for traffic and deliveries.
Summer 2027, weeks 29–34: Railway closes for major construction work
A complete closure of the railway is planned for weeks 29–34. During this period, the pedestrian and cycle underpass beneath the railway and new passing tracks will be constructed.
Work on the station platforms and connecting roads will continue at the same time.
Autumn 2027, weeks 46–49: Railway closes for final works
A further complete closure of the railway is planned for weeks 46–49. The infrastructure will be completed and prepared for connection to the railway network.
December 2027: Pedestrian and cycle underpass and Alnarp station open
The new pedestrian and cycle underpass beneath the railway is scheduled to open in December.
13 December 2027: The new Alnarp train station opens for passenger services.
Spring 2028: Completion and reinstatement of surrounding areas
Work to complete and reinstate the areas surrounding the new station will continue during spring 2028.
One positive effect is that the train station in Alnarp will improve access to campus for students, staff and visitors. The new station will also make it easier to travel sustainably to and from Alnarp.
The new station also means that Sundsvägen will be permanently closed to through traffic at the railway crossing. Instead, a new pedestrian and cycle underpass will be built beneath the railway.
Construction will also affect access to campus and our premises. For example, some roads or areas may be closed temporarily, and some traffic may need to be diverted at various stages.
Lomma Municipality is covering the cost of the station in Alnarp. In 2020, SLU and Akademiska Hus sold land to Lomma Municipality at a reduced price as a form of co-financing.
SLU’s project management team sets up specialist groups as needed to address matters relating to the station. Examples include lighting, measures to compensate for vegetation lost during construction, and specialist expertise relating to teaching and research infrastructure that may be affected by the new station.
Lomma Municipality, SLU and Akademiska Hus have been assured that the current bus services between Lund and Burlöv will continue.
SLU, particularly the departments in the Western Node (Vegetum, Horticum and Articum), has submitted information to the Swedish Transport Administration ahead of the works. Consultants are also carrying out a vibration assessment during autumn 2026 to identify more precisely where sensitive instruments and other equipment are located within the buildings.
The platforms will be located in the area west of Biotronen and Vegetum and north of Sundsvägen. Passing loops will also be constructed as part of the new station development. See the image below.
(The area marked in red shows the location of the platforms, while the green markings indicate the passing loops.)

The project is led by the Swedish Transport Administration and Lomma Municipality, in collaboration with SLU and Akademiska Hus.
Within SLU, the operational work is carried out by a working group consisting of:
The working group is responsible for ensuring that SLU’s interests are safeguarded throughout the project.